Springpole Project

Springpole Project

  • Project Overview
  • Environmental Assessments & Permitting
  • Technical Reports
  • Video and Photo Gallery
  • Newsletter

 

pringpole map First Mining Finance Corp

Project Highlights:

  • One of the largest, undeveloped, open-pit gold deposits in Canada
    • Reserves of 3.8 million ounces gold at .97 g/t, 20.5 million ounces of silver at 5.2 g/t
    • Average annual gold production of 335,000 ounces in years 1 through 9
  • Positive Economics, +11 year mine life
    • PFS announced January 2021, post-tax NPV5%  of $995 million and post-tax IRR of 29%
  • Tier 1 Mining Jurisdiction
    • Long history of gold production in the area
  • Unique Strategic Gold Asset
    • One of the few projects in Canada able to produce more than 300,000 oz per year
  • Existing Infrastructure in Place
    • 70-person camp, access to logging road and power line within 40 km of proposed plant

2021 PFS Highlights(1):

The PFS contemplates an open pit mine and milling operation, evaluating recovery of gold and silver from a 30,000 tonne-per-day operation, with a process plant that includes crushing, grinding and flotation, with fine grinding of the flotation concentrate and agitated leaching of both the flotation concentrate and the flotation tails followed by a carbon-in-pulp recovery process to produce doré bullion.

Key PFS highlights include:

  • US$1.5 billion pre-tax NPV5% at US$1,600/oz gold, increasing to US$1.9 billion at US$1,800/oz
  • US$995 million after-tax NPV5% at US$1,600/oz gold, increasing to US$1.3 billion at US$1,800/oz
  • 36.4% pre-tax IRR; 29.4% after-tax IRR at US$1600/oz gold
  • Life of mine (“LOM”) of 11.3 years, with primary mining and processing during the first 9 years and processing lower grade stockpiles for the balance of the mine life
  • After-tax payback of 2.4 years
  • Declaration of Reserves: Proven and Probable Reserves of 3.8 Moz Au, 20.5 Moz Ag (121.6 MT at 0.97 g/t Au, 5.23 g/t Ag)
  • LOM Metal Recovered 3.2 Moz Au, 18.1 Moz Ag; 3.0 Moz Au, 16.1 Moz Ag (Year 1 to 9)
  • Initial capital costs estimated at US$718 million; Sustaining capital at US$55 million; plus another $29 million in closure costs
  • Annual payable gold production of 335 koz (Year 1 to 9); 287 koz (LOM)
  • Low strip ratio of 2.22 to 1 (Year 1 to 9); 2.36 to 1 (LOM)
  • Head grade of 1.12 g/t Au and 5.7 g/t Ag (Year 1 to 9); 0.97 g/t Au and 5.2 g/t Ag (LOM)
  • Recoveries of 87% for gold and 90% for silver (Year 1 to 9); 86% for gold and 90% for silver (LOM)
  • Total cash operating cost of US$558/oz (Year 1 to 9); US$618/oz (LOM)
  • AISC of US$577/oz (Year 1 to 9); AISC US$645 (LOM)

Note: Base case parameters assume a gold price of $1,600/oz and a silver price of $20/, and an exchange rate (C$ to US$) of 0.75. All currencies are reported in U.S. dollars unless otherwise specified. NPV calculated as of the commencement of construction and excludes all pre-construction costs.

(1) Cash costs consist of mining costs, processing costs, mine-level G&A, treatment and refining charges and royalties.

(2) AISC consists of cash costs plus sustaining and closure costs.

Springpole Mineral Resource Estimate for Gold and Silver at Cut-off Grade of 0.4 g/t Au(1)(2)(3)(4)(5):

Category
Tonnes (Mt)
Grade
Au (g/t)
Grade
Ag (g/t)
Contained Metal
Au (Moz)
Contained Metal
Ag (Moz)
Indicated
151
0.94
5.0
4.6
24.3
Inferred
16
0.54
2.8
0.3
1.4

Notes:

  • Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability;
  • All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate;
  • Open pit mineral resources are reported within an optimized constraining shell using the following parameters:
    • Metal prices of USS 1550 /oz gold, US$ 20/ oz silver, exchange rate of 0.77 USD:CAD
    • Mining cost of CAD$ 1.62 /t, processing cost of CAD$ 15.38 /t milled, G&A of CAD$ 1.00 /t milled
    • Pit slopes varying between 35 and 50 degrees depending on domain
    • Gold recovery of 88% and silver recovery of 93%
  • Open Pit resources are reported at a COG of 0.3 g/t gold.

The Mineral Reserves for Springpole are based on the conversion of Measured and Indicated resources within the current Springpole pit design. The Springpole Gold Project Mineral Reserves are shown below:

Springpole Proven and Probable Reserves (effective December 30, 2020)

Category
Tonnes
(Mt)
Grade
Au (g/t)
Grade
Ag (g/t)
Contained Metal
Au (Moz)
Contained Metal
Ag (Moz)
Proven
0.0
0.0
0.0
0.0
0.0
Probable
121.6
0.97
5.23
3.8
20.5
Total
121.6
0.97
5.23
3.8
20.5

Note: This mineral reserve estimate is as of December 30, 2020 and is based on the new mineral resource estimate dated July 30, 2020. The mineral reserve calculation was completed under the supervision of Gordon Zurowski, P.Eng of AGP Mining Consultants Inc., who is a Qualified Person as defined under NI 43-101. Mineral reserves are stated within the final design pit based on a US$878/ounce gold price pit shell with a US$1,350 /ounce gold price for revenue. The equivalent cut-off grade was 0.34 g/t Au for all pit phases. The mining cost averaged CAD$ 1.94/tonne mined, processing averages CAD$ 14.50/tonne milled, and G&A was CAD$ 1.06/tonne milled. The process recovery for gold averaged 88% and the silver recovery was 93%. The exchange rate assumption applied was CAD$1.30 equal to US$1.00.

 

Follow the link to our Environmental Assessment Portal for up to date detailed information regarding the permitting and engagement programs related to our Springpole Project.

PDAC 2021 Virtual Core Shack

Drill Hole

Video Gallery

Springpole Gold Project - Camp

Video thumbnail image

Springpole Drill Core Shacks

Video thumbnail image

Springpole Gold Project- Aerial View Of Camp, Drill Core Shacks and Bay

Video thumbnail image

Springpole 3D Conceptual Mine Site Plan HD 2 Cut

Video thumbnail image

Join our email list to receive news and updates on First Mining.

Click here to subscribe

Subscribe

Stay up to date with our latest news